Gov’t spends D199M on procurement, usage of quarantine facilities - CTV Africa
According to the National Audit Office (NAO) on the 2022
Government’s Covid-19 response phase-one, the Gambia Government spent GMD199,
979,708 on procurement and the usage of quarantine facilities without
conducting a needs assessment.
The report noted that the team requested evidence of
needs assessment carried out at the initial stage of any procurement activity
but remained outstanding. NAO added that procurement should not be carried out
without proper needs assessment as it is an important activity that ensures
that the required quarantine Centres or facilities are procured and used which
will help avoid wastage of resources.
On the failure to comply with the procurement process and
procedures, NAO revealed that services totalling D8, 995,235 were rendered even
before the request for approval was sent to GPPA. The NAO report further noted that
all proposed contracts for procurement shall be submitted to the authority for
its approval, along with the complete contract file.
The report indicated that contracts were awarded before GPPA
approval was granted, emphasizing that the award for the procurement of quarantine
centres was issued before obtaining approval from the GPPA. It continued that all
proposed contracts for procurement shall be submitted to the Authority for its
approval, along with the complete contract file.
On failure to submit quotations, the institution’s report
revealed that payments of D193, 207,843.00 were sourced through Request for
Quotations, stating that no evidence was provided to confirm this method of
procurement was followed as the list of all the service providers (successful
and unsuccessful) with their respective price quotations were not presented for
review.
“Authorizing officers should ensure that quotations are
requested and provided by at least three independent bidders and the most
responsive bidder is selected before payments are authorized and approved,” NAO
stated.
On its conclusion, the NAO highlighted that based on the
evidence obtained; control weaknesses were identified during the audit as the
audit team did not receive sufficient information and documentation from the Ministry of Health to substantiate the procurement and payment to quarantine
centres or facilities.
The NAO concludes that the Ministry of Health failed
to comply with the public procurement laws and regulations.